Technical and Regulatory Compliance in the Design and Execution of Waterproofing Works
Technical and regulatory compliance in the design and execution of waterproofing works is mandatory to ensure the durability of structures and the acceptance of the works without objections:
- Reference standards and regulations: Standard C 235 (concerning the design and execution of waterproofing) and CR 6 establish the minimum performance requirements for membranes and primers.
- CE marking and Technical Approval: Any material used in construction projects within the Romanian market must have a Declaration of Performance (DoP) based on a valid Technical Approval for construction.
- Quality control on-site: The site supervisor must verify the traceability of batches, the thickness/weight of the membranes, and the successful completion of watertightness tests (water testing).
Legislative Framework and Reference Regulations in Romania
The field of waterproofing in Romania is governed by strict technical standards aimed at preventing structural degradation caused by water infiltration. A site supervisor or a technical supervisor for construction execution (RTE) must be thoroughly familiar with the key technical requirements:
- Standard C 235: Governs the design, execution, and operation of waterproofing systems for buildings using bituminous and plastic materials.
- Standards EN 13707 and EN 13969: Harmonized European standards for flexible bituminous membranes used for roofing and the waterproofing of foundations, respectively.
- Law 10/1995 on Quality in Construction: Mandates the exclusive use of products that are certified (approved) and compliant.
Mandatory documentation upon receipt of materials at the construction site
When bituminous membranes and primers are delivered to the construction site, the site supervisor must verify the presence of the product’s technical documentation. The absence of even a single document from this list may result in the rejection of the entire batch:
| Technical Document | Role and Main Content | Issued By | On-site Verification Criterion |
|---|---|---|---|
| Declaration of Performance (DoP) | Attests to technical properties (cold flexibility, elongation, tensile strength). | The manufacturer (based on the CE marking). | Correspondence between the batch code on the membrane roll and the DoP. |
| Technical Approval for Construction | National approval for the use of the product under specific conditions in Romania. | Accredited certification bodies (e.g., CICE, INCERC). | Validity of the document and the specific approved areas of use. |
| Safety Data Sheet (SDS) | Information regarding handling, storage, and protective measures (e.g., for solvents). | The manufacturer / distributor. | On-site storage conditions (no direct exposure to sunlight or sources of fire). |
| Warranty and Traceability Certificate | Confirms the guaranteed service life and the certified batch number. | The manufacturer / authorized supplier. | Ensuring that the quantities delivered correspond to the surface areas specified in the execution project. |
Checklist for the Site Supervisor: From Inspection to Water Testing
To ensure flawless execution, on-site inspections are carried out in three critical stages:
Stage A: Inspection of the Substrate
- The concrete surface is primed uniformly, free of dust spots, and with a moisture content not exceeding 4%.
- Slopes toward drains conform to the project specifications (minimum 1.5–2%).
- Fillets and junctions at parapets have a radius of at least 5 cm (rounded corners).
Stage B: Inspection of the Installation Process
- Longitudinal overlaps are at least 8–10 cm, and transverse overlaps are 15 cm.
- During torch-on application, a continuous bead of molten bitumen (1–2 cm) is visible along the edge.
- For mineral-surfaced (slate-finished) membranes, the mineral layer has been removed/stripped away in the overlap areas.
Stage C: Watertightness Test (Flood Testing)
- Mandatory before the installation of protective layers or paving slabs. The terrace is flooded with 5–10 cm of water for 48 hours.
- There must be no signs of moisture on the underside of the slab or at the parapet junctions.
Frequently Asked Questions
Yes. According to Romanian legislation (Law 10/1995, as amended), for certain specific construction applications, a valid Romanian Technical Approval is required; this document certifies that the product complies with local climatic conditions and national standards.
Without the official report (minutes) confirming the watertightness test via flooding, the acceptance inspection for the critical stage—specifically regarding waterproofing—cannot be signed off by the site supervisor or the ISC (State Construction Inspectorate) inspector.